This article outlines the steps to installing the Endurance Charger Panel in your depot.
Important: This work must be carried out by a licensed or certified electrician. The incoming supply must be protected by a 16 A overcurrent device, and the installation must comply with applicable electrical regulations.
Before installation
Confirm that:
- the chosen location is indoors, sheltered and well ventilated;
- the mounting surface can support up to 20 kg;
- there is sufficient clearance for cabling, batteries and safe working;
- the required isolation and circuit protection have been provided; and
- all panel and isolator switches are in the Off position.
Mount the panel
- Use the drilling template to mark the mounting holes.
- Check the panel position with a level.
- Drill the mounting holes. Use a 12 mm masonry drill bit if you are using the supplied fixings on a suitable masonry surface.
- Fit fixings that are suitable for the wall construction.
- Use two-person handling to lift the panel into position.
- Secure the panel and confirm that it is level and stable.
The top of the panel should be mounted no higher than 1.8 m from the floor.
Connect the power supply
Traffic Group Signals recommends connecting the charger panel to an independently protected supply with:
- suitable circuit isolation;
- isolation for each charging panel;
- 16 A overcurrent protection for the incoming supply; and
- suitable conduit or trunking to protect the installation.
The total connected load must not exceed the maximum current rating of the isolator or supply circuit.
- Install the required isolation switches and protected supply in accordance with the installation design.
- Confirm that the main isolator, panel isolators and charger-panel switches are Off.
- Connect each panel to its isolator using the IEC 60309 2P+E plug and lead.
- Check the earth bonding and all electrical connections.
- Complete the required electrical inspection and testing before putting the system into use.
Commission the panel
- Turn the main isolator On.
- With the charger-panel switch still Off, connect a compatible battery using the Anderson connectors.
- Turn the charger-panel switch On.
- Check that the Test LED illuminates or flashes and that the charger begins its test sequence.
- Confirm that Normal mode is selected.
If all charger status LEDs flash, switch off and disconnect the system immediately. Check for reverse polarity, a short circuit, an unsuitable battery or another fault before the charger is used again.